West Coast Main Line
Optilan has
installed a total of 440 kilometres of optical
fibre cabling trackside, together with associated
fibre splicing, termination and test, for Prime
Contractor telent (formerly
Marconi Communications)
.Optilan was also awarded a separate contract
to provide splice bays, constructing
around 200 splice bays in all.
The contract ran for approximately 20 months,
involving between 18 and 28 suitably skilled
and qualified Optilan Engineers at work on site
at any one time
. |